Mike, Kerry and Brian came over today to install our new cabinets. They were delivered a week ago and have been sitting in my garage waiting for this day to come. It has been a super long process and a lot of sweat and hard work, but things are really starting to take shape!
Category: Chandler Arizona House
This house was built in 1984 and sits on a 19,000 square foot culdesac lot. The back yard has amazing potential.
Final Touches Before Cabinets
Mudding and Primer
Installing New Ceiling Drywall – Day 2
We started at 10am and finished at 9:30pm. What a long day! We managed to get most of the drywall up on the ceiling and around the upper wall. This was a very tough job. I am sure that Mike Holmes would not approve of our work, but I am pretty happy with the way it turned out (especially for a bunch of amateurs).
Installing New Ceiling Drywall – Day 1
Karl and Greg came over to help me get started with installing the new drywall on the kitchen ceiling. Doing drywall on the ceiling is MUCH more difficult and time consuming than I anticipated. It took us three hours to get two sheets up with the cutouts for the lights and vents. I know, I know, we are a bunch of amateurs!!
New Wiring and Can Lights
Remove Drop Ceiling Framing
Finally we are in the home stretch of removing the awful drop ceiling. Mom worked hard removing the framing and I helped as much as I could in my leg brace. Notice the timestamps on the before and after. This took us 3 hours. Not too bad.
Notice the very bad wiring job that was up there. We are going to fix that for sure!
Moving Water Line and Exhaust Pipe
Remove Kitchen Drop Ceiling Day 2
Today Aloha Air is rerouting our AC from the drop ceiling hard vent into flex tubing in the attic. This is a big job but will make our AC much more efficient. We also had a new thermostat and return register installed.
Then Mom and I continued the demolition of the drop ceiling.
Next we need to remove the light box, reroute the plumbing and electric and then drywall the new ceiling.